98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project Resourcing
Project Resourcing
Resolved · Low Priority · Version 2007
David has attended:
Project Intermediate course
Project Resourcing
I am trying to develop a system that will allow me to report on the capacitiy of 4 staff members. Each member has 1 Project file. All are connected to one strategic overview file that shows their combined workload. I need to be able to the percentage of their time that each task takes, and therefore the percentage of their time that their workload as a whole takes (ie, are they overallocated).
How do I get them to input the % of their time that a task will take over its duration, without effecting the duration of the task?
RE: Project Resourcing
Hi David
Thanks for your question. It sounds like you have experienced tasks changing duration when resources are added or removed.
If a task doesn't necessarily go faster because more resources are working on it or slow down because someone leaves the task (meetings are a good example of this) then try splitting the screen (Window > Split) clicking on the task in question and removing the tick from Effort Driven, followed by OK. Now add or remove your resources and the Work will change, not the duration.
If you are adjusting assigned units and finding durations are changing incorrectly change the Task Type. It's just below the Effort Driven tick box on the split screen. Try setting it to fixed duration, clicking OK then adjusting the Unit percentages of your resources. Again you will find the duration remains unchanged but Work will be affected. It's useful to have the Work column added or perhaps Cost so you can keep an eye on the impact of changes you make.
Let me know if this helps or if you have any further questions.
Kind regards,
Andrew
Mon 30 Aug 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |