project server consulting - pert charts

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server consulting - PERT charts

project server consulting - PERT charts

resolvedResolved · Low Priority · Version Standard

Daniel has attended:
Project Intro Intermediate course

PERT charts

Can I change the project in the PERT chart (Network Diagram) view?

RE: PERT charts

yes, double click on the task you wish to change, and then change the task information details


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.1 secs.