View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » project training in london - RESTRAINTS
project training in london - RESTRAINTS
Resolved · Low Priority · Version Standard
Joe has attended:
Project Intro Intermediate course
RESTRAINTS
Can I delete a restraint straight from the task bar?
RE: RESTRAINTS
Hi Joe
It looks like you may be enquiring about Constraints that have been added to a task. All tasks have a constraint the default being "As soon as possible". If your task has some other kind of constraint set then switching back to this default setting will have the effect of releasing the task from date constraints. To do this double click on the task and go to the advanced tab. From here set the constraint type to "As soon as possible". Don't worry about clearing the date box to the right - when you click on OK Project will remove any constraint date set.
I hope this is helpful - do let us know if you require further information.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Formatting Bar TextTo display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK. |