microsoft project training - project question

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training - Project 2003 Question

microsoft project training - Project 2003 Question

resolvedResolved · Low Priority · Version Standard

Lee has attended:
Project Intermediate course

Project 2003 Question

Is there any way to delete an item once it has been indented?

it seems alittle strange that once you have indented a task you cant undo it

RE: Project 2003 Question

Hi Lee

Yes the indenting of items can take a little while to get used to. The principle is that if you indent a task then the row above it becomes a summary (by default it goes bold and its duration is now that of the tasks indented below it)

To stop a task being a summary task you need to outdent the tasks below it. Once a summary task has nothing indented below it then it returns to being a regular task.

To outdent a task simply right click on the task and from the menu that appears choose outdent.

One other point to bear in mind is that if you delete a summary task Project will warn you that it will also remove any of the tasks indented below it.

Hope this helps - let us know if you need further information or if you have other questions.

Kind regards,

Andrew


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.08 secs.