Manpower Loading & Manpower Histogram
Resolved · Urgent Priority · Version 2003
Daniel has attended:
Project Introduction course
Project Intermediate course
Project Advanced course
Manpower Loading & Manpower Histogram
Hi,
I now need to show Manpower loading for each engineering function & activity with an appropriate histogram.
Please advise on the best method ?
Many Thanks,
Daniel
RE: Manpower Loading & Manpower Histogram
hi Daniel
Here's a link to a short video showing how to do Manpower loading. It shows how to split the screen into 2 windows (Windows, Split) so that in the bottom window you can change the view to Resource Graph. This is a good way to display a Manpower Histogram.
http://www.youtube.com/watch?v=F9WT02SJ3xE
I hope that helps for now. Please send let us know if you want more details.
Doug Dunn
Best STL
Fri 11 Oct 2013: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |