View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » MS Project Recurring task creation
MS Project Recurring task creation
Resolved · Urgent Priority · Version 2010
Olufemi has attended:
Project Intro Intermediate course
Project Advanced course
Project Intro Intermediate course
MS Project Recurring task creation
Is it possible to create a recurring task on a set of tasks, that is on a summary task.
I have a deployment to 236 sites and I have a set of tasks recurring. I want to be able to create a schedule to set the summary task that has the detailed tasks recurring.
Example as in below, to create a recurring task on the summary task "Test Configuration"
Test Configuration
<indented> Enrollment
<indented> Intersol
<indented> Clean Conficker virus from PCs
<indented> Receipt Printer on Tellers PCs
<indented> Sign-off Branch Upgrade
<indented> Travel to Next Branch
Many thanks
RE: MS Project Recurring task creation
Hi Olu
Thank you for your question. Recurring tasks are created individually rather than a recurrence being set on the summary task.
Would you be able to achieve the effect you are looking for by creating the first set of tasks, with dependencies and summary task then copying and pasting the block of tasks for each new deployment. You could then set start no earlier constraints for each set of tasks by keying in start dates in the start column.
I hope this helps - if I've misunderstood your question please tell me more and I will try to be of further help.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |