View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » microsft+office+project+2003+courses+in+london - Milestones
microsft+office+project+2003+courses+in+london - Milestones
Resolved · Low Priority · Version Standard
David has attended:
Project Intro Intermediate course
Milestones
Why do my milestones all move to the same end date, despite having links to earlier tasks?
RE: Milestones
David
as discussed after you had posted your question, you had scheduled from the end dates and did not have a link from the milestone to another task then project puts it in the only place it knows, at the end date.
hope this ansewrs your question
regards
david
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |