microsoft+project+training - resource report customisation

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft+project+training - Resource Report Customisation

microsoft+project+training - Resource Report Customisation

resolvedResolved · Low Priority · Version Standard

Bronwyn has attended:
Project Advanced course

Resource Report Customisation

How do I customise the resource usage report to include the project name / summary tasks for each task. At the moment I can not see which project a resource's task relates to.

RE: Resource Report Customisation

Hi Bronwyn

Unfortunately crosstab reports such as this one can't be modified to add further columns to the display. However you might want to approach this in a different way and rather than create or modify a report simply modify the resource usage view (View > More views > resource usage) And add the fields you wish to display (e.g. project and name) and from file > page setup prepare the view for printing.

Hope this helps Bronwyn - do let us know if you have further questions.

Kind regards,

Andrew


 

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Server loaded in 0.07 secs.