Resourcing #2
Resolved · Medium Priority · Version 2003
Bradley has attended:
No courses
Resourcing #2
When assigning resources to a project or task, how can I show the resource name on the Gantt chart? Can I then filter by resource name so only the projects/tasks assigned to that person are populated?
RE: Resourcing #2
Hi Bradley
Thank you for your question
Resource names should appear on the Gannt chart as standard. If not you can add them by clicking on Format-Bar styles, selecting the text tab and adding resource names at the appropriate point.
Filtering is indeed possible. You can click on the autofilter button on the toolbar and select the resources you wish to see in the filter drop down list above the resources column in the gantt chart table
Again, this is covered on our project intro/intermediate course
Regards
Stephen
Tue 26 May 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Gantt ChartsGantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts |