Microsoft Project - Gantt charts

resolvedResolved · Low Priority · Version 2007

Kate has attended:
Project Introduction course

Microsoft Project - Gantt charts

How can I change all of the bars colours to something other than blue? I would like all of them to be purple to match our corporate colours.

Thanks

Kate

RE: Microsoft Project - Gantt charts

Hi Kate

Thank you for your question - you can set the colours by using Format > Bar Styles. From the dialogue box that appears make sure the Task style is selected and choose the colour thatis closest to your corporate style from the selector.
The colour you have chosen will apply to current and future tasks.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Thu 9 Apr 2009: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)