Holiday in Resourse Graph and Resource Usage
Hi!
My question is if MS Project can show Holidays in the Resource Graph/Usage view when the Holidays are entered in the Resource Pool!?
How can i do that?
Thanks a lot
Stefanie
RE: Holiday in Resourse Graph and Resource Usage
In short, yes they will appear.
The longer answer is you need to make sure you use the "Work" Resource Graph (not Peak Units) and "Show Availability Line".
Hope this helps!
J Black
http://www.pmconnection.com
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |