How do I cater for resources that work 1/2 and full days..

resolvedResolved · Low Priority · Version 2003

How do I cater for resources that work 1/2 and full days..

where a half day is >5 and <8 hours and full day >8 hours?

RE: How do I cater for resources that work 1/2 and full days..

Hi Shrevas

Thank you for your question. If you have a mixture of resources. Some of whom work part time and others who work full time you may want to create a dedicated part-time calendar which has shorter working days (Tools > Change working time > New) and then in the resource sheet in the set the base calendar value for your part-time resources to the new calendar you created.

I hope this helps - let me know if you have any further questions.


Kind regards,
Andrew

Mon 19 Jan 2009: Automatically marked as resolved.


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Server loaded in 0.09 secs.