How do I cater for resources that work 1/2 and full days..
Resolved · Low Priority · Version 2003
Shreyas has attended:
Project Intro Intermediate course
Excel Intermediate course
Excel Advanced course
Visio Advanced course
Project Management - Framework & Processes course
Presentation Skills course
How do I cater for resources that work 1/2 and full days..
where a half day is >5 and <8 hours and full day >8 hours?
RE: How do I cater for resources that work 1/2 and full days..
Hi Shrevas
Thank you for your question. If you have a mixture of resources. Some of whom work part time and others who work full time you may want to create a dedicated part-time calendar which has shorter working days (Tools > Change working time > New) and then in the resource sheet in the set the base calendar value for your part-time resources to the new calendar you created.
I hope this helps - let me know if you have any further questions.
Kind regards,
Andrew
Mon 19 Jan 2009: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |