How do I show the tasks only for the project to print for the client?

RE: MS Project

Hi Orion

Thank you for your question. You can hide elements such as summary tasks very quickly by going to Tools > Options > View and deselecting "Show Outline tasks" and then clicking on OK.

You can now see a simplified version of your Gantt chart, minus summary tasks and their bars.

Hope this helps - let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)