Hi
I have used the indent button on a sub task by 'accident' and made it into a Summary task... I need to bring this back into line ie stop it being a summary taks and return it to a sub task. (I'm currently clicking on the Outdent button and nothing is happening!)
How do I do this please?
Thanks
Jo
RE: Sub Tasks
Hi Jo,
You need to select the subtasks underneath the task you accidently turned into a summary task. Then click on the OutDent button. This should return the task to a subtask.
I hope this has answered your question.
Regards
Simon
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |