MSP
Have found progress line fails to pick up progress in advance of status date, although works for progress on status or behind. Help please!
RE: MSP
Dear Stephen
Thank you for your question
Progress lines usually are based on a tasks cumulative percentage completion up to the specified point, in your case the status date.
I suggest that first you set the percent complete spreads to the status date. To do this click on Tools-Options-Calculation and then click on
the Edits to total task % complete will be spread to the status date tickbox
Hopefully, this will set the progress line up correctly. If you still have problems please let me know, so we can explore other possibilities
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |