training in microsoft project - ms project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » training in microsoft project - MS Project 2007 - Timescale

training in microsoft project - MS Project 2007 - Timescale

resolvedResolved · Low Priority · Version Standard

John has attended:
Project Intro Intermediate course

MS Project 2007 - Timescale

My project shows an overall 7.82 day duration this might be made up of three sub tasks of 3 days 4 days and 3 days a total of 10 days, my question is why the difference and how do I overcome the problem?

The one thing I have attempted to change is the working hours, which Monday

RE: MS Project 2007 - Timescale

Hi John

Thank you for your question

You must first make sure that the calandar options located under Tools-options-calendar, are set the same as your defined base calendar.

You then need to make your base calendar your project default calendar, by clicking on project-information and selecting the relevant calendar in the combo box.

Finally, if you have any resources assigned to the task with different working hours to the project default calendar, then this will alter the duration of the task.

As to making Saturday a work day. Click on the change working time option and select the working time tab. Then select the option button for Saturday and manually type the hours in.

Hope this helps

Regards

Stephen

RE: MS Project 2007 - Timescale

Many thanks Stephen


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.