project server consultants - Task dependency
Resolved · Low Priority · Version Standard
Farzana has attended:
Project Intro Intermediate course
Task dependency
Can a task have a start/start dependency and finish/finish with the same task?
RE: Task dependency
Hi Farzana
Thank you for your question
To do as you described you would have to link to same tasks together twice, one on a Start to Start, and one on a Finish to Finish. Project will not allow you to do this.
One solution would be to arbitrarily divide each of the tasks into two smaller tasks. Simply break task 1 into task 1a and task 1b, and link finish to start. And then divide task 2 into task 2a and task 2 b and link finish to start.
You could then link task 1a and 2 a on a start to start, and task 1b and 2b on a finish to finish. This would have the effect of constraining both the start and the finish of both tasks.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |