project 2007 server training - microsoft projects

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » project 2007 server training - Microsoft Projects

project 2007 server training - Microsoft Projects

resolvedResolved · Low Priority · Version Standard

Tom has attended:
Project Intro Intermediate course

Microsoft Projects

How do I insert weekends?


Regards

RE: Microsoft Projects

Hi Tom

Thank you for your question.

Could you clarify what you mean by insert weekends?

Do you mean how do you make weekends working time? If so then the solution is to define a base calendar which has Saturday and Sunday set as working time. Simply click on tools-change working time and then follow the procedure for creating a new base calendar.

If this calendar is to be the default for the project then you will need to set the total hours for the week on the tools-options-schedule tab.

Regards

Stephen


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.