ms project server training courses - Tasks
Resolved · Low Priority · Version Standard
RE: Tasks
Hi Alan
Thanks for the question
There are four types of task constraint. These are
Finish to Start
Finish to Finish
Start to Start
Start to Finish
The most commonly used would be Finish to Start
Hope this is useful
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |