Tasks

How many task dependicies are there?

RE: Tasks

Hi Alan

Thanks for the question

There are four types of task constraint. These are

Finish to Start
Finish to Finish
Start to Start
Start to Finish

The most commonly used would be Finish to Start

Hope this is useful

Regards

Stephen


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.09 secs.