Forum home » Delegate support and help forum » Microsoft Project Training and help » server course london - Project

server course london - Project

resolvedResolved · Low Priority · Version Standard

Neil has attended:
Project Intro Intermediate course
Access Intermediate course

Project

Is it possible to set up a repeating project, rather than a repeating task

RE: Project

Hi Neil

Thanks for your question. Repeating projects isn't an option in Project. The closest you might get to this might be to create a macro to build multiple projects for you or perhaps generate them manually using a template.

Kind regards,

Andrew


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.