How can I show many different items on the same task (bar)line ?
RE: project
Hi Garry
Thanks for your question.
First create a summary task with indented items below it.
Select the indented items and press shift + F2 to bring up the multiple task properties dialog box. On the general tab click in the box Roll up Gantt Bar to summary so that a tick is in the box. Click ok.
Next double click your summary task and on the general tab put a tick in the hide task bar check box.
Finally click on the minus symbol beside your summary task to fold up the indented tasks leaving only the rolled up bars appearing on one line.
I hope this is helpful - please do let us know if you need further information.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |