ms+project+training - progress line printing

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms+project+training - Progress Line printing

ms+project+training - Progress Line printing

resolvedResolved · Low Priority · Version Standard

Richard has attended:
Project Intro Intermediate course

Progress Line printing

When i display progress lines they will not print, the icons on the progress bar print but no line linking them together, but they are shown in the print preview. Tried to print out on various different printers with no success.

RE: Progress Line printing

Hi Richard

Thanks for your question. I have not been able to recreate the problem you have encountered. You might want to experiment with the zoom level of your timescale and also take a look at the formatting of your progress bar at Tools > Tracking > Progress Lines > Line styles.

Secondly try creating a new test project and apply your progress lines to a couple of sample tasks. If you encounter the same problems printing please forward your example to info@stl-training.co.uk and we can take a look at it.

Kind regards,

Andrew


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips