What are the likely qustions I might be asked in interview as per ms project?
Please am still not yet clear as per the resources allocation as regards effort driven
RE: ms project
Hi Bunmi,
Thank you for the question
It is difficult to say what potential employers will ask about project at an interview. It might be a good idea to say that you have recently been on an MS Project course and list the things that we covered. You can find this informtion on our website.
As to the second part of your question, effort driven tasks are those which can have their duration altered with the addition or removal of resources. For example if you are digging a garden and it takes 2 people 3 days to do it, adding an extra person might reduce the time it takes.
However, if the task was a meeting that was schduled to last for a day; then adding extra people to the meeting would not alter the duration of the task. In this case the meeting would not be effort driven
I Hope this helps
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |