How do you identify hanging depedency
RE: Hanging Depedency
Hi Steve,
Simply add the successors column to the GANTT chart. To do this click right click on a column head and select insert column and choose successors.
Then activate the autofilter and choose NA. If NA doesn't appear, there will be a blank row in the drop down and you should select this.
Any items that then appear in the filtered that are not outline tasks, or the final milestone will need to be linked to the final milestone on a Finish to start basis.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |