project server consultants - Resource Allocation
Resolved · Low Priority · Version Standard
Sarah has attended:
Project Intro Intermediate course
Resource Allocation
I will work 100% on the project until a certain milestone and then will work only 50%. How can I make that automatic in Project?
RE: Resource Allocation
Hello Sarah,
Thanks for your question.
This is possible but you would need to write a fair amount of VBA code and it would be pretty difficult. The effort is probably not worth the result and your best bet would be simply change your availability at the scheduled time for the milestone, and then attach a note reminding you to cahnge it if the milestone date changed.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |