training project server - Costs
Resolved · Low Priority · Version Standard
James has attended:
Project Intro Intermediate course
Costs
Is it possible to measure costs, actual vs planned?
RE: Costs
Hi James
Thanks for your questions. It is possible but before Project can gather the necessary data you need to save a baseline (Tools > Tracking > Save baseline).
In the Gantt Chart view switch to the Costs table (View > Table > Costs) Here you will see costs, baseline and variance information calculated for you.
As you update your project these figures will automatically adjust.
I hope this is helpful - do let us know if we can be of further assistance.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |