training project server - costs

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » training project server - Costs

training project server - Costs

resolvedResolved · Low Priority · Version Standard

James has attended:
Project Intro Intermediate course

Costs

Is it possible to measure costs, actual vs planned?

RE: Costs

Hi James

Thanks for your questions. It is possible but before Project can gather the necessary data you need to save a baseline (Tools > Tracking > Save baseline).

In the Gantt Chart view switch to the Costs table (View > Table > Costs) Here you will see costs, baseline and variance information calculated for you.

As you update your project these figures will automatically adjust.

I hope this is helpful - do let us know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.08 secs.