project server training course - MS project Intro/Intermediate
Resolved · Low Priority · Version Standard
Caroline has attended:
Project Intro Intermediate course
MS project Intro/Intermediate
What is effort driven?
RE: MS project Intro/Intermediate
The three task types are fixed units fixed-unit task: A task in which the assigned units [or resources] is a fixed value and any changes to the amount of work or the task's duration do not affect the task's units. This is calculated as follows: Duration x Units = Work. fixed-work task: A task in which the amount of work is a fixed value and any changes to the task's duration or the number of assigned units [or resources] do not affect the task's work. This is calculated as follows: Duration x Units = Work. fixed-duration task: A task in which the duration is a fixed value and any changes to the work or the assigned units [that is, resources] don't affect the task's duration. This is calculated as follows: Duration x Units = Work.). Project uses fixed units by default. When working with effort-driven scheduling, keep the following in mind: The effort-driven calculations apply only after the first resources are initially assigned to the task. After the first resources are assigned, the work value doesn't change as new resources are assigned to or removed from the same task.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |