Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training course - MS Project 2000

ms project training course - MS Project 2000

resolvedResolved · Low Priority · Version Standard

Joanne has attended:
Project Intro Intermediate course
Project Intro Intermediate course

MS Project 2000

I have a large existing MS Project 2000 document with approx 1200 lines, I need to add another part to the project. This extra piece has been set up in MS project by someone else. When I try to copy and paste this in, or if I try to import it as a project, it changes the dates on the overall project.

Is there any way I can avoid this? I have to add and track plans in the large programme that come from various sources.

All the calendars and versions are the same.

RE: MS Project 2000


Joannee

As per our discussion, I think you need the service packs to resolve these issues.

info@stl-training.co.uk


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)