ms project courses - Resource pool

resolvedResolved · Low Priority · Version Standard

Jenny has attended:
Project Introduction course
Project Intermediate course

Resource pool

I am using a resouce pool for a number of different projects. Some of the names in the resource pool are now red, indicating that there are clashes in the calendar for the use of these resource people.
Is there a way of using the software to identify these clash points please?

RE: Resource pool

Jenny

Use the Resource Usage view to identify what days and by how many hours the names are over allocated.

regards


david

RE: Resource pool

Thanks for this. I have now used the resource usage view, and have been able to see the places where there are several tasks for different projects allocated on the same day to the same person! I have created a new column in the resource usage view, to identify the names of the projects, as I have a number of projects running in parallel, with similar tasks, and I needed to identify which was which. However, I have now found that some of the discrepancy of allocation is because some projects appear twice on the list in resource usage, although I have only one document for each project. Can you please let me know how I can handle this? Many thanks

Jenny


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips