How do I put a lag of 3 hours between two tasks?
RE: MS Project
Hi Henrietta,
You add lag (and lead) time to the link that joins your tasks.
Double click on a link and from the dependency dialogue box that appears add the amount of lag you require.
If you make links between tasks by double clicking the task and choosing the predecessor tab you will see that when you choose your predecessor you can also specify lag or lead time.
I hope this helps - do let us know if you have any further questions
Kind regards,
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |