How do I put a lag of 3 hours between two tasks?

RE: MS Project

Hi Henrietta,

You add lag (and lead) time to the link that joins your tasks.
Double click on a link and from the dependency dialogue box that appears add the amount of lag you require.

If you make links between tasks by double clicking the task and choosing the predecessor tab you will see that when you choose your predecessor you can also specify lag or lead time.

I hope this helps - do let us know if you have any further questions

Kind regards,

Tracy


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.