ms project training - Time records

resolvedResolved · Low Priority · Version Standard

Chris has attended:
Project Intro Intermediate course

Time records

Is it possible to use MS Project to record times worked by different contributors?

RE: Time records

Hi Chris

Thanks for your question - the answer relates directly to your other post. The Resource Usage view lets you record actual time-phased work completed (from the format menu choose Details then Actual Work)

Once you have baselined your project you can also double click tasks in this view to update actual work carried out by the resource. Although it's not quite as detailed as using the full sheet you do still get to allocate work carried out on a resource by resource basis.

If we can be of any further help please do let us know.

Kind regards,

Andrew


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips


Server loaded in 0.09 secs.