RE: calendars
Hi Sharon
Thanks for your question - from the Tools menu in Gantt chart view click on change working time... From this dialogue box you can set working and non working days for your calendars as well as create new calendars.
To choose a calendar to apply to your entire project go to the Project menu then Project information and choose the calendar on which you would like to base your project.
I hope this answers your question - do let us know if you need any further information.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |