microsoft project london courses - Project 2003

resolvedResolved · Low Priority · Version Standard

Andy has attended:
Project Intermediate course

Project 2003

How can I install a task complete % bar on an already active bar?

RE: Project 2003

GO to INSERT > COLUMN and select % COMPLETE then click OK

this install a task complete % bar


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips