course ms project - Costs
Resolved · Low Priority · Version Standard
RE: Costs
Hi Jay
When you assign a resource that has a cost associated with it then Project will work out the cost of that task.
Alternatively you can simply add cost information directly to your task. In Gantt chart view, right click on one of your columns and from the context menu that appears choose the cost field
You can now directly enter cost figures for your tasks, whether they have resources assigned to them or not.
Hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |