Critical Path
Resolved · Medium Priority · Version 365
Seamus has attended:
Project Intro Intermediate course
Critical Path
What do i specifically need to input to generate a critical path. I have put together a basic programme and linked some of the tasks but the system does not produce a critical path. Do i need to link all items with predecessors?
RE: Critical Path
Hello Seamus,
Thank you for your question. To show the critical path in MS Project, you need to go to the Gantt Chart Format tab, then tick the box next to Critical Tasks.
Your tasks do not necessarily need to be linked to show critical path. Project will shade the task or combination of linked tasks which determine the finish date of your project in red.
I hope this helps.
Kind regards
Marius Barnard
Senior Trainer
STL
Wed 29 Nov 2023: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |