Predecssors are not following on in dates

I am setting predecessors but the dates are not following on or corelating accordingly and am unsure why?

RE: Predecssors are not following on in dates

Hello Ryan,

Thank you for your question. Without the benefit of seeing your project, my best guess is that the 'Calculate project after each edit' option in your Project app is turned off.

To fix this, please do the following:
Click File > Options > Schedule. Scroll down to 'Calculation'.
Make sure that the 'On' option is selected.

If this doesn't solve your issue, please use the forum again for further assistance.

I hope this helps.

Kind regards
Marius Barnard
STL

Tue 12 Jul 2022: Automatically marked as resolved.


 