Adding Sub-projects to a Master Schedule
Resolved · Medium Priority · Version 2010
Colin has attended:
Project Intermediate course
Adding Sub-projects to a Master Schedule
when adding a sub-project to a Master Schedule the Sub-Project appears with the name of a previously added sub-project, yet the detail is is correct.
RE: Adding Sub-projects to a Master Schedule
Duplicate question - answer in original post
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |