View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Costing
Costing
Resolved · Urgent Priority · Version 2016
Edward has attended:
Project Advanced course
Costing
I am trying to set up a costing template for projects but am having a problem with my milestones cause an "ERROR" message in the rollup of the %Prof. Forecast (see details below).
1. How do I remove the cost associated to 0 hrs duration on a milestone so that I am not dividing by zero?
2. Is there a better field to use if I want to apply a % margin to a number?
I have set up all my costs e.g:
Labour Travel Total %Prof. Revenue Budget Actual %Prof.
Cost Cost Cost 10% Forecast Cost Forecast
Labour Cost - Cost1
Travel Cost - Cost2
Total Cost - Cost1 + Cost2
%Prof. = [Number1]&"%"
Revenue Forecast = (Total Cost/(1-%Prof.)
Budget = Revenue Forecast
Actual Cost = Input as a duration
%Prof. Forecast = (Revenue Forecast-Total Cost)/(Revenue Forecast)
RE: Costing
Hi Edward
Thank you for using the forum
Could you perhaps send the file to info@microsoft-training.co.uk
I'd like to take a look at the file to get a better idea of what's happening in it
With thanks and kind regards
Wendy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |