london course ms project - Task types and effort driven tasks

resolvedResolved · Low Priority · Version Standard

Narinder has attended:
Project Intro Intermediate course

Task types and effort driven tasks

Hi,

When entering tasks - is this the point where you should decide whether your task is fixed unit, work or duration and after the decision whether the task type should be effort driven or not?

What are the common factors in deciding how to make this decision?

OR do you use Project defaults of fixed unit and effort driven and wait until you assign resources and then are prompted to choose a task type with warning triangle ?

I know that adding resources to a task, changing its type and deciding whether it is effort driven or not are ways to reduce scheduling conflicts but is it correct that deciding task type is too late at this stage.

Thanks for any help
Narinder

RE: Task types and effort driven tasks

Narinder

It all depends on the task you wish to use, have you any specific examples you would like to share..


regards

dave

RE: Task types and effort driven tasks

I have 2 tasks of 5 days each as a duration.
The first is a database analysis task with a one person assignment of 40%.
The second is a programming task with multiple (2)assignments of 40% and 50%.
The calendar I am using is a 7 hour each day calendar.

RE: Task types and effort driven tasks

Narinder

Sorry for late reply, but i cannot find a right answer to this answer have you?

david


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.