Microsoft Project - Task bar length
Resolved · Low Priority · Version 2016
stephen has attended:
Excel Intermediate course
Project Introduction course
Microsoft Project - Task bar length
When preparing a project I notice that some task bars show almost no length, although they are for the same duration (e.g. 5hrs) as the other before and after them. If I expand the Gantt chart sufficiently the bars will pop out to represent the same length as others. Why does this happen, please?
RE: Microsoft Project - Task bar length
Hi
Thank you for using the forum to ask a question.
The bars draw through non-working time making the task look longer.
When you are zoomed out it's trying to show you a task that starts on one day and rolls over and finishes on another. Hence the longer bar.
When you zoom in your scale turns into hours and it shows accurately.
Kind regards
Richard Bailey
Microsoft Certified Trainer
Best STL - https://www.stl-training.co.uk
98%+ recommend us
London's leader with UK wide delivery in Microsoft Office training and management training to global brands, FTSE 100, SME's and the public sector
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |