multiple baselines

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Multiple Baselines

Multiple Baselines

resolvedResolved · Urgent Priority · Version 2016

Stephen has attended:
Project Intermediate course

Multiple Baselines

I have been asked to review a programme and setup up monthly Baselines from May 2016 - Mar 2017 showing the progress( or not) of each task (2000 in total)on a monthly basis to highlight the lack of performance of the contractor.

I have all the programems but a separate one for each month

How do I do this?

I need to complete this by 28/03/17

I have tried setting up the baselines, but it has not been successful.

RE: Multiple Baselines

Hello Stephen,

Thank you for your question regarding Ms Project Baselines.

All our Ms Project trainers are delivering training today, but will be able to respond on Monday.

Kind regards,

Richard

RE: Multiple Baselines

Hi Stephen,

I think what I understand from your request is that you need a way of seeing the changes Month by Month between the two dates.

Baselines
Multiple baselines should have been taken as each file was saved so that the Mar 2017 version had all of the baselines. Rather than going back to baseline all files individually and trying to compare that I think you might need to use Project Comparison

Project Comparison
Open up one of the Programme files
On the Report Tab, click on Project Comparison
Browse and Select another Programme file (different month)
Click OK and let it generate a report
This should show you the difference between the two files.
If you did this with the May 2016 file and compared it with each Month, it should give you the incremental changes between the two files.
The May 2016 and March 2017 comparison should give you the total slippage/delay by the contractor.

Please can you try comparing the files and let us know

Kind regards

Richard Bailey
Microsoft Certified Trainer

Best STL - https://www.stl-training.co.uk
98%+ recommend us

London's leader with UK wide delivery in Microsoft Office training and management training to global brands, FTSE 100, SME's and the public sector

Sun 2 Apr 2017: Automatically marked as resolved.


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips


Server loaded in 0.07 secs.