Splitting the colour of the bar with a formula - for days over t
During our course on the 2nd day. Garry had shown us a formula to use to highlight the days over with colour coding through a formula. I have forgotton to send the file to myself. Would it be possible for him to provide this file or some other file with the formula and instructions Please?
RE: splitting the colour of the bar with a formula - for days ov
Hi Refiya
thanks for your message - we'll check the code and post to you.
Andrew
RE: splitting the colour of the bar with a formula - for days ov
Hi Refiya
I now have the example file and will email it to you today.
If you have further questions please do let us know.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Inserting Task Durations QuicklyWhen entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day. |