Forum home » Delegate support and help forum » Microsoft Project Training and help » Columns on gantt chart

Columns on gantt chart

resolvedResolved · Low Priority · Version 2007

Karen has attended:
Project Introduction course

Columns on gantt chart

can a 'week' column in the gantt chart be highlighted, eg to show a school half term, but continue as working time

RE: Columns on gantt chart

Hi Karen

I don't think there's a way of highlighting working time such as half term. One way though would be to use the Drawing tools and draw a coloured rectangle representing the period. Drawing object can be sent behind the task bars by right click, Arrange.

This is not a good solution if you zoom to a different timescale though.

Doug Dunn
Best STL

RE: Columns on gantt chart

Thanks for the suggestion. I'm putting my new found skills to the test this morning by setting up my own programme so I'll give it a go but appreciate the limitations!

RE: Columns on gantt chart

Great to put your skills into action.
Good luck Karen!

Fri 4 Oct 2013: Automatically marked as resolved.


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.27 secs.