courses microsoft project london - Finish Dates / Links
Resolved · Low Priority · Version Standard
Peter has attended:
Project Intro Intermediate course
Finish Dates / Links
If your project has a finish date but not a start date how do I work backwards from the finish date to establish a start date?
Thanks
RE: Finish Dates / Links
Hi Peter,
Thanks for your question. The fastest way to link two tasks is to click on the bar of your first task in the Gantt chart and drag to the bar of the task that will be your successor. Once you let go you'll get a link drawn between your tasks, Finish to Start.
You can also block select multiple tasks and click on the link icons task. You can also double click on the successor task and from the predecessors tab choose the task you want to link to.
Hope this helps - do let us know if you have any further questions.
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |