RE: Project.
Hi Amina
Thank you for your question. You can move a project using the Move button which is on the Project ribbon. When you use this button a dialogue box will open and allow you specify a new date. The project is moved to the date and any constraints in your plan are adjusted so any Slack is preserved.
I hope this helps - do let me know if you have any further questions.
Kind regards,
Andrew
Thu 8 Dec 2011: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |