RE: links
john
go to the task you wish link to and type in the ID number of the task you are linking from, ie
ID Task Name ....................Predecessor
1 dig trench
2 mix foundation material 1
3 lay foundation 2
hope this answers your question
regards
david
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |