Budget
How do you calculate earned value on your project?
RE: Budget
Hi Jenny
Thank you for your question. MS Project can calculate Earned Value information for you. All your project needs are costed resources assigned to tasks and a saved Baseline. To see the built-in Earned Value tracking take a look at the View ribbon then choose Tables > More Views
In this list you will find an Earned Value table along with two variations (one showing cost the other schedule indicators).
I hope this helps - do let me know if you need any further information.
Kind regards,
Andrew
Mon 17 Oct 2011: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |