standard constant calculation du

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Standard Constant for Calculation in Duration Field

Standard Constant for Calculation in Duration Field

resolvedResolved · Medium Priority · Version 2007

Igors has attended:
Project Intro Intermediate course

Standard Constant for Calculation in Duration Field

Hello!

Using formulas for calculation duration we often need to use number of minutes for working day as some constant. For example: 480 for 8-hours working day or 450 for 7.5 h.

If there is some standard constants which contain actual number of minutes for working day in standard, project or user's calendar. It would be useful to not change formulas in custom fields.

RE: Standard Constant for Calculation in Duration Field

Hi Igors,

Thank you for your question.

The only work around I can think of is to go to Tools and then Options and on the Schedule and choose Duration entered in Hours instead of days. This change will convert the duration to hours.

I hope this helps.

Regards

Simon


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Server loaded in 0.07 secs.