Forum home » Delegate support and help forum » Microsoft Project Training and help » Working time.

Working time.

resolvedResolved · High Priority · Version 2007

Shonna has attended:
Project Intro Intermediate course

Working time.

For some reason my plan thinks Sunday is a working day and I don't know how to swich it off. I have checked the calendar and it says it is a non working day. But when I place a task on the plan the resource is working through Sunday!

RE: Working time.

Hi Shonna,

Thank you for your question and welcome to the forum.

There may be three reasons to why this is happening:

1. When a task is 6 days and starts on Thursday, the task would finish on the Thursday of the next week. The Gantt bar will stretch across the non working time (Sat and Sun).

2. Check Tools and Change Working Time. See if there are any exceptions that make the Sunday a working day.

3. Go to the Resource sheet and double click on the resource you assigned the task to. Click on the Change Working Time button and check whether there are any exceptions to the rule.

I hope this helps.

Regards

Simon


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.08 secs.