Please can you let me know how to import the excel sheets into MS proj 2010
Thanks
Vanita
RE: MS PROJECT 2010 IMPORT TO EXCEL
Hi Vanita,
Thank you for your question.
To start the Import Wizard you need to follow these steps:
1. Go to File and Open.
2. Select Excel Workbook from File Types and select the Excel workbook and click Open.
3. This will start the Import Wizard and follow the steps through.
4. When you get to the Task mapping screen you need to choose which worksheet contains the data you want in project.
5. You then need to choose and map the fields from Excel into Project fields.
I hope this answers your question.
Regards
Simon
Sun 5 Dec 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |